December 2012
Presentation of the feasibility study for the consolidation of the IOC headquarters to the Executive Board.
March 2013
Launch of the international architecture competition. More information, click here.
June 2013
Selection, by the architecture competition jury, of the 12 architects invited to develop a project for the new IOC headquarters.
December 2013
Choice of the architecture competition laureates by the competition jury and the IOC Executive Board.
January 2014
Launch of the Parallel Development Studies with the three architecture competition winners.
April 2014
Choice of the preferred architecture partner for the consolidation of the IOC headquarters by the Executive Board. More information, click here.
December 2014
Presentation of the Olympic House project to the 127th IOC Session. More information, click here.
3 March - 2 April 2015
Deconstruction permit public inquiry. More information, click here.
10 April 2015
100-year anniversary of the IOC in Lausanne.
30 June - 30 July 2015
Request for the Olympic House building permit.
8 December 2015
Symbolic laying of the first stone of the new IOC Headquarters. More information, click here.
February 2016
Launch of archaeological studies on the Vidy site and start of deconstruction.
Summer 2016
Construction starts on Olympic House.
23 June 2019
Inauguration.